当前位置:服务支持 >  软件文章 >  BIM模块化施工应用范例—越南Cao lanh混凝土斜拉桥项目解析

BIM模块化施工应用范例—越南Cao lanh混凝土斜拉桥项目解析

阅读数 4
点赞 0
article_banner

BIM模块化施工应用范例 —越南Cao lanh bridge(混凝土斜拉桥)

The Cao Lanh Cable-Stayed Bridge is a component of the Central Mekong Delta Connectivity project, which is also the principal element of the project. The bridge is 2010m long. Completion is scheduled to be in 2017. The estimated maximum price set for this project is 250 million USD. 

blob.png

blob.png

This is a complex project with strict requirements on its technical standards since it has to comply with both Vietnamese and international standards. Therefore, the project requires a lot of experience in calculation and design. Besides, one of the most intensive tasks in this project is to keep up with very tight schedules requested by main contractor. This mission would not be possible without the use of BIM technology. In this project, we chose Tekla solution to model the whole bridge in a 3D environment. The bridge model will not only be used for Shop drawings production but also will play an important role in the operation and maintenance period of this project.

blob.png

blob.png

Special Challenges
After a short period of time getting familiar with Tekla, VTCO decided to apply this technology on Cao Lanh Bridge, which is a large cable-stayed bridge. The team basically lacked experience of working with the software and they faced many difficulties in organizing overall model management, dividing into logical sections for manipulating on Tekla and Tekla BIMSight later on and organizing manpower for each logical component model.
This is a big project with complex structure and dense structure of reinforcement. At one point the team got stuck in an early stage of this project. Since this was the first time for VTCO to use Tekla software on a project, they did not have the system of regulations in the working process. Many times, the selection of options to solve the problem was faced with trouble, resulting in having to change the solution in the end. This led to uncertainty of schedules. In the implementation period of the Cao Lanh Bridge project, they had to spend nearly 40% of their time on studying and adjusting product to be in accordance with client’s requirements (investors required them to arrange drawings using the old ways). The model was in large file size, which caused restrictions during manipulation. To ensure the submission regulations, exporting drawings from the model also was faced with many difficulties, because investors required standards of drawing arrangement very tightly.

blob.png

Project's Success Factor
Initially, there were some difficulties that the team had to cope with and VTCO’s management Board found this software highly efficient so they tried to apply it and obtained successful results from it. This also was a factor that motivated their engineers to invest more time in researching and developing the works. The Management Board’s effort was shown in giving engineers a hands-on training course in WSP, Finland in April 2014. They gained invaluable knowledge from that training course. Owing thanks to that, they could correct any mistake and applied faster options in designing with high productivity and efficiency. In a short time (nearly 6 months), they became very well acquainted with the model and applied it on this project. After using the model, they helped investors resolve the conflict points of steel in structures very intuitively and accurately. A key point in the success of this project happened when the team realized the importance of studying Tekla’s open API for their work.

blob.png

BIM模块化施工应用范例 —越南Cao lanh bridge(混凝土斜拉桥)的图7

BIM模块化施工应用范例 —越南Cao lanh bridge(混凝土斜拉桥)的图8

Project Civil Works Data:

BIM模块化施工应用范例 —越南Cao lanh bridge(混凝土斜拉桥)的图9

  • Contractor: China Roads and Bridges Corporation (CRBC) and VINACONEX E&C JV

  • Contract Amount: USD 144,388,531

  • Contract Commencement Date: 25 March 2014

  • Contract Duration: 1038 days

  • Contract Completion Date:  22 October 2017

Detailed Design and Supervision Consultant:

  • CDM Smith Inc, -  Yooshin Engineering Corporation  -   WSP Finland  -  Joint Venture

BIM模块化施工应用范例 —越南Cao lanh bridge(混凝土斜拉桥)的图10

Cable Stayed Bridge Structure.

  • The Cao Lanh Bridge will be a 650m long cable-stayed bridge, with a central span of 350m and a maximum clearance above high water level of 37.5m.

  • The total length of the bridge including the approach viaducts will be 2,014.74 m. The approach bridge uses Super T Girders.

  • The overall span arrangement is (1 x 39.15 + 15 x 40 + 1 x 37.8) + (150 + 350 + 150) + (1 x 37.8 + 15 x 40 + 1 x 39.15).

BIM模块化施工应用范例 —越南Cao lanh bridge(混凝土斜拉桥)的图11

Bridge Pylon.

BIM模块化施工应用范例 —越南Cao lanh bridge(混凝土斜拉桥)的图12

Bridge Cross-Section.

BIM模块化施工应用范例 —越南Cao lanh bridge(混凝土斜拉桥)的图13




免责声明:本文系网络转载或改编,未找到原创作者,版权归原作者所有。如涉及版权,请联系删
相关文章
QR Code
微信扫一扫,欢迎咨询~

联系我们
武汉格发信息技术有限公司
湖北省武汉市经开区科技园西路6号103孵化器
电话:155-2731-8020 座机:027-59821821
邮件:tanzw@gofarlic.com
Copyright © 2023 Gofarsoft Co.,Ltd. 保留所有权利
遇到许可问题?该如何解决!?
评估许可证实际采购量? 
不清楚软件许可证使用数据? 
收到软件厂商律师函!?  
想要少购买点许可证,节省费用? 
收到软件厂商侵权通告!?  
有正版license,但许可证不够用,需要新购? 
联系方式 155-2731-8020
预留信息,一起解决您的问题
* 姓名:
* 手机:

* 公司名称:

姓名不为空

手机不正确

公司不为空